Accessory Dwelling Units are now legal in most of Massachusetts, but building one is not a simple task. This guide walks through the ADU construction process step by step, including Boston.
Short answer: The ADU construction process in Massachusetts runs in three phases: design and survey (typically 1 - 2 months), permitting (typically 1 - 2 months), and construction (about 17 weeks, or roughly 120 days, for a single-story ADU on Horizon ADU's schedule). That is 11 steps and roughly 5 - 8 months in total. Boston projects that need Zoning Board of Appeal (ZBA) approval take longer.
Key Takeaways
- Inspections gate every stage: footings before the pour, the foundation before backfill, rough trades and framing before insulation, insulation before drywall, and final inspections before occupancy.
- Every foundation, even a slab on grade, needs frost walls 4 feet (48 inches) deep.
- Payments follow construction milestones, and Massachusetts home improvement law limits the deposit to one-third of the contract price.
The ADU construction process at a glance
| Phase | Steps | Typical timing |
|---|---|---|
| Design and survey | 1. Feasibility and design | 1 - 2 months |
| Permitting | 2. Construction documents and permitting | 1 - 2 months |
| Construction | 3. Site preparation through 11. Final touches and punch list | About 17 weeks / 120 days (single-story) |
| Total | All 11 steps | About 5 - 8 months; Boston ZBA projects 11 - 16 months |
For what extends or shortens each stage, see our guide to how long it takes to build an ADU in Massachusetts.
How is ADU construction different?
An ADU (Accessory Dwelling Unit) is a small, fully independent home on the same lot as an existing house, with its own kitchen, bathroom, entrance, and utilities. It can be detached (a stand-alone backyard home), attached to the main house, or internal (a basement, attic, or other space converted inside the existing home).
ADU construction differs from standard home building in three ways. State and local rules overlap, and many towns are still working the 2025 state law into their bylaws, which is why we recommend a builder with local ADU expertise. ADUs are infill projects, built around an existing home, its utilities, and tight setbacks. And ADUs typically cost more per square foot, because documents, permits, foundation work, utility connections, and a kitchen and bath are needed whether the project is 500 or 2,500 square feet.
Can you build an ADU in Massachusetts?
Short answer: In most of Massachusetts, yes. Outside Boston, state law allows one ADU by-right in single-family zoning districts, as long as it is under 900 sq ft or 50% of the main home's gross floor area, whichever is smaller. Boston has its own rules.
The Affordable Homes Act, whose ADU provisions took effect February 2, 2025, applies to any lot with an existing dwelling in a zone that allows single-family homes. Here is what applies statewide (outside Boston), even when an ADU is by-right:
- One ADU under 900 sq ft (or 50% of the principal dwelling's gross floor area, whichever is smaller) is allowed without a special permit or variance in single-family zoning districts.
- Towns cannot require you to live on the property.
- Towns can require at most one additional parking space, and none within half a mile of public transit.
- You still need a building permit, compliance with the Massachusetts State Building Code (780 CMR) and the state ADU regulations (760 CMR 71.00), sewer or Title 5 septic compliance, and a Certificate of Occupancy before anyone can live in the unit.
The by-right law is Sections 7 and 8 of Chapter 150 of the Acts of 2024; see the state's official summary of the ADU law. Setbacks and other details are still left to each town, so check our Massachusetts ADU regulations guide and your local building department.
Boston is its own zoning district, and the state law does not apply. An ADU in Boston can be an additional legal unit that can be condoized, but approval can take much longer; see our guide to Boston vs. state ADU rules.
Which construction method should you use?
Manufactured (HUD-code) homes do not qualify as an ADU in Massachusetts. Modular ADUs are partly factory-built and can work; stick-built ADUs are built entirely on site, which offers the most flexibility on tight lots. This guide follows the stick-built process; see our prefab vs. stick-built comparison.
Step-by-step ADU construction process
The ADU construction process has eleven main steps. Construction itself (steps 3 - 11) typically takes about 17 weeks for a single-story ADU on Horizon ADU's schedule. Here is how those weeks usually run:
| Stage | Duration | Weeks |
|---|---|---|
| Mobilize, clear and excavate | 1 week | 1 |
| Footings (inspected), frost walls, foundation inspection, backfill | 2 weeks | 2 - 3 |
| Utility trenches and underground plumbing, then slab | 1 week | 4 |
| Framing: floor, walls, roof, sheathing | 3 weeks | 5 - 7 |
| Roofing, windows, exterior doors (weathertight) | 1 - 2 weeks | 7 - 8 |
| Rough plumbing, electrical, HVAC (siding goes on at the same time) | 2 - 3 weeks | 8 - 10 |
| Trade rough inspections, then framing inspection | 1 week | 10 |
| Insulation and insulation inspection | 1 week | 11 |
| Drywall: hang, tape, finish | 2 weeks | 12 - 13 |
| Paint, interior doors and trim | 1 week | 14 |
| Cabinets, counters, flooring, tile, bath | 2 weeks | 15 - 16 |
| Finish plumbing, electrical and HVAC; appliances | 1 week | 16 |
| Final grading, punch list, final inspections, Certificate of Occupancy | 1 week | 17 |
The durations add up to more than 17 weeks because some stages run in parallel: siding goes on during the rough-ins, and trenching can start while the foundation is being poured.
1. Feasibility and Design
First, confirm the ADU can be built within your budget. A feasibility study looks at utilities and setbacks, plus often-overlooked items like topography, easements, and site access. The design then follows what can be built and your budget, from a model floor plan or a custom design.
This is also the time to sort out financing. If you are using a bank loan or HELOC, qualify before signing a contract and paying for construction documents; see our guide to ADU financing.
As an approved provider through the MHP ADU Incentive Program, we can provide this feasibility study at no cost to you. You can see whether your property qualifies using our ADU Planner, and we will contact you about a feasibility study.
2. Construction documents and Permitting
Most Massachusetts towns require these documents, completed and stamped by licensed professionals, for a building permit:
- A floor plan and "elevations" showing what the exterior will look like
- Structural drawings showing how the building will be framed and the foundation constructed
- A plot plan showing where the ADU will sit and how utilities will connect
- A HERS energy rating report showing how insulation, windows, and HVAC affect energy efficiency
The building department usually comes back with a few questions, which the contractor answers before the permit is issued. While the permit is in review, the homeowner makes finish selections so materials are ready when construction begins. We pull separate electrical, plumbing, gas, and mechanical permits through licensed tradespeople and schedule every municipal inspection. Approvals can add time: on one lot in an aquifer protection district, the footprint needed a ZBA special permit, which took about 3 months and about $800 in fees.
3. Site preparation
The project manager walks the site, the ADU's corners are marked, and a portable toilet is delivered. We strip the topsoil in the work area, stockpile it on site, and reuse it around the finished ADU.
4. Site Work and Utility Connections
The excavation team clears and grades the area, removing a patio or driveway or preparing for a retaining wall if needed. Trenches are dug to where water and sewer connect, either in the existing home's basement or at the street, and utility pipes are run and connected. Underground electrical service is run now; overhead service is run once the ADU is framed.
Electrical service came up on most jobs Horizon ADU has priced: either a 100 to 200 amp upgrade of the main house or a new, separately metered 200 amp service for the ADU. Horizon ADU's quotes typically include a new electric meter but exclude utility-company work such as transformer upgrades or pole relocation. On septic lots, the Board of Health inspects the septic system after it is installed.
5. Foundation
ADU foundations are typically a slab or a crawl space, both on footings of about 12 by 12 inches set below the frost line, which is 48 inches in Massachusetts. A slab is the most cost-effective, with plumbing run before the concrete is poured. A crawl space gives easier access to plumbing and can be used for storage.
Every foundation we build, including a slab on grade, gets 4-foot frost walls. Footings are inspected before the pour, and the foundation must pass inspection before it is backfilled. Stepped footings, ledge, unsuitable soils, buried debris, and groundwater are handled as change orders.
6. Framing
The floor (on a crawl space), walls, roof structure, and plywood sheathing go up, then the interior partition walls.
7. Exterior finishes
The roof, windows, and exterior doors make the shell weathertight; siding to match your main home follows during the rough-ins.
8. Rough Mechanical
Plumbers run water lines, drains, and roof vents; electricians run wiring and boxes for outlets, lights, and appliances; and the HVAC installer runs refrigerant, electrical, and drain lines for a ductless mini split, the most common ADU system. Each trade's rough inspection, then the framing inspection, must pass before insulation goes in.
9. Insulation, Drywall and Plaster
Insulation is typically spray foam, which seals air gaps better, or fiberglass batts, which cost less. It is inspected to confirm the building meets energy requirements. Drywall then goes up on walls and ceilings, finished with a coat of plaster.
10. Interior Finishes
Tile goes into the bathroom, followed by finish carpentry (interior doors, trim, cabinets, and countertops), flooring, and paint. Lighting, faucets, and appliances go in last, when the design choices made earlier become visible.
11. Final touches and punch list
A walkthrough covers cleaning and small adjustments, then the town's final inspections. The Certificate of Occupancy is issued only after they pass.
How do payments work during ADU construction?
We bill against construction milestones, typically 5 - 10 payments, with the last payment due only after final inspections pass and the occupancy permit is issued. Massachusetts home improvement law limits the deposit to one-third of the contract price. An example five-payment schedule:
| Payment | Milestone | Share of contract |
|---|---|---|
| 1 | Deposit at contract signing | 15% |
| 2 | Permits and approvals issued | 25% |
| 3 | Building envelope substantially complete | 30% |
| 4 | Insulation and interior work | 20% |
| 5 | Completion and municipal sign-off | 10% |
Change orders are written and signed: changes of $5,000 or less are paid in full at signing, and larger changes are paid half at signing and half on completion.
What is the homeowner’s role during ADU construction?
Your main role is making finish selections (cabinets, countertops, fixtures, flooring, tile, lighting, windows, and doors) on schedule so ordering is not delayed. Selections are priced against allowances: if a choice costs more or less, the contract price adjusts through a written change order. Our standard work hours are Monday - Saturday, 7am - 5pm, and once work starts we commit to continuous progress. Finish landscaping, patios, and extra parking are typically excluded from the build price.
How does Massachusetts weather affect ADU construction?
Frozen ground makes excavation, trenching, and concrete pours harder and costlier, with ground-thawing equipment and heated enclosures for curing. Many towns also have a winter moratorium on street openings that can delay utility connections until mid-April. Framing and roofing continue in cold weather, more slowly.
What does ADU construction cost?
The two main cost drivers are size and the difficulty of utility connections. Typical ranges are $150,000 - $250,000 for a basement or garage conversion, $150,000 - $325,000 for an attached ADU, and $200,000 - $360,000 for a detached ADU.
| Item | Price |
|---|---|
| Single-story ADU, 900 sq ft | $290,000 - $320,000 (about $320 - $360 per sq ft) |
| Soft costs (design, survey, civil engineering, HERS report, permit, utility fees, ZBA filing, fire protection plan) | About $15,000 |
| Full basement under a 900 sq ft single-story ADU | About $10,000 added |
Costs rise with septic replacement (pre-1995 Title 5 systems often need it), a grinder pump on lots that slope away from the sewer, a sprinkler system for Boston ADUs more than 50 feet from the street, and the Specialized Stretch Energy Code some towns have adopted. For the full breakdown, see how much it costs to build an ADU in Boston.
Frequently asked questions
How long does the ADU construction process take in Massachusetts?
Typically about 5 - 8 months from design to move-in. Design and survey take 1 - 2 months, permitting 1 - 2 months, and Horizon ADU schedules about 17 weeks (roughly 120 days) of construction for a single-story ADU. Boston projects that need ZBA approval take about 11 - 16 months.
What is the maximum size of an ADU in Massachusetts?
900 sq ft, or 50% of the main home's gross floor area, whichever is smaller. That is the by-right limit in single-family zoning districts outside Boston.
Do I need a building permit if my ADU is by-right?
Yes. By-right removes the special permit or variance, but you still need a building permit, separate trade permits, State Building Code (780 CMR) compliance, Title 5 or sewer compliance, and a Certificate of Occupancy.
What is the first step in building an ADU?
A feasibility study of your lot. Setbacks, access, utilities, topography, and septic capacity determine what can be built before you pay for design.
How much deposit can an ADU builder require in Massachusetts?
No more than one-third of the contract price. That is the limit under Massachusetts home improvement law. Later payments should follow construction milestones.
Does the statewide ADU law apply in Boston?
No. Boston is its own zoning district and follows its own ADU rules, which can mean a longer approval process.
Do I have to live on the property to build an ADU?
No. Outside Boston, state law prohibits owner-occupancy requirements, so you can build and rent an ADU without living on the property.
How many parking spaces does an ADU need?
At most one additional space, and none within half a mile of public transit. That is the limit the state places on what towns can require.
Next steps
As Paul, a client in Milton, put it: "They provide quality workmanship and the team is highly responsive during both the design and construction phases."
If you are still exploring, start with our ADU Planner to see what your property may support. As an approved MHP ADU Incentive Program provider, we can provide a feasibility study at no cost to you. When you are ready to talk through your project, contact us.